The UWM Student Union Renovation Project will be completed according to the following timeline.
Early Fall Semester 2021
- Exterior concrete repair to Union façade
- Prepare for new generator in Pangaea Mall
Late Fall Semester 2021
- Column footing reinforcement in Gasthaus and northeast exterior stairs
Winterim 2021-2022
- Reinforce building columns on all building levels to support new mechanical and HVAC penthouse on roof
- Construction begins in lower level of previous bookstore to become the future home of Centers for Advocacy and Student Engagement (CASE)
- Inclusive Excellence Center (IEC)
- Lesbian, Gay, Bisexual, Trans Resource Center (LGBTRC)
- Military and Veteran’s Resource Center (MAVRC)
- Women’s Resources Center (WRC).
- Student Organization offices and storage areas on 3rd floor emptied
Early Spring Semester 2022
- Ongoing construction of lower level of previous bookstore for CASE
Late Spring Semester 2022
- Full office closures of
- Student Involvement
- Union Cinema
- Union Art Gallery
- Studio Arts and Crafts Centre
Summer 2022
- Commencement May 22nd
- Full building closure on May 23rd
- PantherCard office temporarily relocated
Fall Semester 2022
- Union re-opens
- New locations for:
- Center for Community-Based Learning, Leadership & Research (CBLLR)
- University Legal Clinic
- Neighborhood Housing Office
- Panther Shop
- Books by eCampus
- UWM Tech Store
- PantherCard office
- Event services
- Opening:
- All Union Campus Level Dining units
- Closed: Union Art Gallery, 8th Note Coffeehouse, Gasthaus
- New locations for:
Spring Semester 2023
- On-going renovations
- Opening:
- Gasthaus
Summer 2023
- Full building closure: June-August
Fall 2023
- Anticipated Grand Reopening