9/30/21 – Project Charter Sponsor Sign-off (Revised Version 3.0)
Data Collection Phase (IN PROGRESS)
10/31/21 – Determination of costs to operate each UWM building
2/28/22 – Assessment of Current Use and Allocation of Space
8/31/23 – Identification of Future Space Needs
8/31/23 – Assessment of current conditions of each UWM building
Data Analysis Phase (NOT YET STARTED)
Planned Start Oct/Nov 2021 – Alignment of Space Optimization Project with UWM’s strategic plans (including 2030 planning)
Planned Start April/May 2022 – Gap Analysis of Current Space Use compared to Future Space Needs
Implementation Phase (NOT YET STARTED)
TBD – Recommendations to address the gap between Current Space Use and Future Space Needs
TBD – Recommendations for funding plan to right-size and improve campus space to meet current UWM’s current and future needs
TBD – Implementation Approach, Options & Timeline for approved recommendations to address the gap between Current Space Use and Future Space Needs
Process Improvement & Continuation (ONGOING)
TBD – Identification of campus space procedures, forms, processes that need to be updated to maintain a long- term ability to respond to future space needs and assessments
TBD – Assessment of Space Data management tools needed to enable long term space analysis and adjustments